This project will be done over 6 phases (trips). The 1st, 3rd and 5th phases will be the de-installation of existing equipment in two rooms, each trip. Each room has 1 Stryker anesthesia boom, 1 Stryker equipment boom, 2 Stryker light flat panels, 1 Stryker SPI integration system, flush mounted speakers and a wall control unit. Once the equipment is removed our KR Wolfe technicians will build crates for the larger pieces of equipment and box the smaller items. These will all be placed in a mobile storage unit at the facility and re-installed a couple months later.
The 2nd, 4th and 6th phase will involve un-crating the product, re-cabling and installation of the removed equipment.